Labelling Machine FAT Checklist UK
Home/Guides/Labelling Machine FAT Checklist UK

Factory acceptance test checklist for labelling machines

A labelling FAT should test real containers, real label rolls, line speed assumptions, changeover points and the faults most likely to appear on site.

Why this matters

A labelling FAT should test real containers, real label rolls, line speed assumptions, changeover points and the faults most likely to appear on site. It is important because FAT planning, samples, labels, acceptance criteria and test formats can change the required label head, product handling, sensor choice, conveyor layout, operator access and acceptance test.

Many labelling quotations fail to capture the difference between a machine that can apply a label during a demonstration and a machine that will run reliably with live products, live labels and real operators. The details below help turn a broad enquiry into a specification a supplier can work with.

Specification checklist

  • Product dimensions, shape, material and surface condition.
  • Label dimensions, material, adhesive, liner, core size, gap and unwind direction.
  • Label position, placement tolerance and whether front/back, wrap-around, top, bottom or side application is required.
  • Output target, product spacing, changeover frequency and line speed.
  • Coding, barcode, date, batch or variable data requirements.
  • Existing conveyor, line layout, guarding, access and utilities.
  • Acceptance criteria for trials, installation and commissioning.

Selection guidance

Choose the simplest machine that will still control the product correctly. Round containers generally need reliable rotation and wrap pressure. Flat, oval or rectangular containers need side control and repeatable label-head timing. Flat products, boxes and pouches need stable presentation to the label head. Case and pallet applications often depend more on data integration and print quality than on the applicator alone.

When comparing suppliers, check what is included: product handling, conveyors, sensors, printer integration, installation, training, spares and aftercare. A lower machine price can become expensive if the application needs extra controls or support after delivery.

Useful enquiry pack: product photos, dimensions, sample labels, label roll specification, target output and a simple line sketch.
Common checks

Questions to answer before specification

Why does FAT planning, samples, labels, acceptance criteria and test formats matter?

It affects machine choice, label accuracy, line speed and the risk of rework. It should be confirmed before equipment is quoted.

What should be checked before asking for a quotation?

Confirm pack dimensions, label roll details, label position, output target, surface condition and any coding, inspection or conveyor integration requirements.

Can Lancing UK advise on the correct route?

Yes. Lancing UK can review product and label information and recommend a suitable labelling machine route for the application.

Want Lancing UK to review your labelling requirement?

Send the application details and samples so the correct machine route can be checked before quotation.

Final technical depth

Test the agreed requirement, not only a demonstration run

A factory acceptance test should show that the configured machine meets the agreed scope under defined conditions. It is most valuable when products, labels, operating states and acceptance criteria are prepared before the visit.

Freeze the test scope

Link each test to the quotation, approved requirement or design record. Identify items that can only be completed after installation.

Control the test materials

Reference every product and label roll used, including whether it is a production item or prototype. Record any difference from final materials.

Test change and recovery

Normal running alone misses many practical issues. Include format change, roll change, start/stop, representative faults and controlled restart.

Record evidence and deviations

Use a result sheet with pass, fail, observation and action. Agree responsibility and closure evidence for every deviation.

Decision evidence

What to define and test

Use the table to turn a broad requirement into evidence that can be reviewed during sample trials, FAT, installation and handover.

AreaWhat to establishPractical check
Machine configurationModel/configuration, options, guards, sensors and supplied interfacesMatches approved scope and drawings
Format trialsRepresentative minimum/maximum products and labelsStable feed, label presence, position and finish
ChangeoverChange parts, settings, recipes and operator accessRepeatable method and recorded settings
Controls/faultsStarved, blocked, label end, sensor, printer and permitted interlocksCorrect alarm, stop and recovery behaviour
DocumentsAvailable manuals, drawings, parts and setting recordsRequired draft pack available for review
Open actionsItems deferred to site or requiring correctionOwner, due point and objective closure evidence

Buyer checklist

  • Circulate the FAT protocol before the test.
  • Bring the agreed products and production-quality label rolls.
  • Define run duration or sample basis without inventing an arbitrary target.
  • Include the intended operator and maintenance representatives where practical.
  • Photograph or retain accepted samples with identifiers.
  • Do not treat site-dependent interfaces as passed at the factory unless genuinely simulated.